From Q3 2023 and into 2024, Vinje Industri was engaged by NEL Hydrogen Electrolyser AS for inspection, production, and mechanical and piping installation during the development phase of their test center in Notodden.


NEL Hydrogen Electrolyser AS was the client in the project and maintained direct and daily dialogue with our team throughout the execution phase.


Scope of Work

Vinje Industri delivered a complete set of services including:


  • Site inspection and evaluation

  • Joint assessment with the client to identify improvement needs

  • Project management

  • 3D scanning and engineering

  • Planning and coordination of execution, including correct lifting equipment

  • High HSE focus throughout the work, resulting in an incident-free execution

  • Pipe production, procurement, transport, and delivery

  • Welding and welding inspection

  • Solution-oriented and skilled installation personnel


With a focus on safety, flexibility, and quality, the project was executed in close collaboration with NEL Hydrogen’s team and other stakeholders on site.



"Throughout the project, Vinje Industri has been flexible, solution-oriented, worked efficiently, demonstrated strong collaboration with other parties, and taken responsibility for solving their assigned tasks within deadlines. This has resulted in high-quality solutions and significant cost savings. We’ve had a very good experience with Vinje Industri on this project and can warmly recommend their services for similar projects."

— Jan Inge Kvamme, Project Manager, NEL Hydrogen Electrolyser AS

This project is a great example of Vinje Industri’s ability to support forward-looking energy solutions with solid execution, professional teamwork, and a proactive approach to both safety and efficiency.